Project: Scaffold for solar panel removal.

Location: Lyminster Road, Wick, Littlehampton, BN17.

Project overview: This case study details the planning and execution of scaffolding provision for the removal of a solar panel at a property in Littlehampton. The primary objective was to construct a safe and stable working platform that would enable technicians to access and remove the solar panel efficiently.

Scope of Works

The scaffolding requirement for this project was specific:

Scaffold type: Access tower.

Dimensions:

Base: Approximately 2.4 metres (length).

Height: Approximately 7.0 metres (4 lifts).

Platform configuration:

Ladder access lift: 5 boards deep.

Top lift (working platform): 9 boards deep.

Safety ladder gates installed.

Challenges and considerations

While seemingly straightforward, several factors were considered during the planning phase:

  • Height and access: The 7.0-metre height necessitated a robust and stable scaffold tower to ensure worker safety at this elevated level.
  • Working platform size: The 9-board deep top lift was crucial in providing ample space for technicians to manoeuvre while allowing enough room for tools and equipment and ensuring the safe handling of the solar panel during removal.
  • Ladder access: The 5-board deep ladder access lift ensured a safe and comfortable ascent and descent for personnel.
  • Site specifics: While the immediate area around the property was clear for scaffold erection, potential ground conditions or obstructions were assessed during a pre-site visit.
  • Cost-effectiveness: Providing a suitable and safe scaffold within a reasonable budget was a key objective.

Solution

Based on the requirements, an approximate 2.4 metre long by 7.0 metre high access tower was supplied and erected. The scaffold incorporated:

  • Four scaffold lifts: Providing progressive access to the 7.0-metre working height.
  • Ladder access: Integrated within the scaffold structure on one side, with a generous 5-board deep platform to facilitate safe entry and exit at each lift.
  • Spacious top lift: The critical working platform, located 7.0 metres high, was constructed 9 boards deep, providing a broad and secure area for the solar panel removal team. This depth is vital for the safe handling of potentially awkward solar panels.
  • Safety features: Standard scaffolding safety features, including guardrails, toeboards, and appropriate bracing, were implemented to comply with safety regulations and best practices.

Cost and duration

  • Scaffold hire cost: £550 + VAT.
  • Hire duration: 1 week.

This pricing model provided the client with a cost-effective solution for the relatively short duration required for the solar panel removal.

Outcome

The scaffolding was successfully erected at this location, providing safe and efficient access for the solar panel team. The spacious working platform and secure ladder access contributed to a smooth, safe operation, minimising the risks associated with working at height. The project was completed within the allocated period, demonstrating the effectiveness of choosing the right scaffolding solution. We have also delivered many other reliable access solutions across Littlehampton, including a 9m-high tower for flat roof replacement on Colebrook Road and a 3-storey decorating scaffold at The Old Wareham Mews. View more of our Littlehampton scaffolding projects here or call 01903 331490 for a free scaffold quote.